SYSTHERM s.r.o.
+420 377 241 177
E-mail: info@systherm.com
Implementation information
- Investor: Teplárna Písek, a.s.
- Implementation: 2012
- Description: Within the framework of the realisation of the works, the existing steam and secondary hot-water distribution system in the area of Písek – Budějovické předměstí – Sever were replaced with a more efficient hot-water two-pipe distribution system. A steam/water transfer station was built, which was deployed in the existing ZŠ Tylova transfer station. The rated output of this block transfer station was 9 MW. A primary 110/50 line runs from this exchanger station in FINTHERM pre-insulated pipe technology for the rest of the offtakes in the area of Budějovické předměstí – Sever.The steam line connection from the current trunk steam line to the Tylova transfer station was executed using “steel-in-steel” vacuum pipe technology from FW FERMWÄRNE-technik GmbH.